CN / EN

Singapore Labrador I 230kV UGSS Underground Substation Project

The Labrador Underground Substation is part of the Urban Redevelopment Authority’s 2019 Master Plan. Located on the site of the former Pasir Panjang Power Station, it is Singapore’s first underground substation capable of handling 230kV electrical load.

Scope of Service: Supply and installation of 66kV outdoor terminations

图片4
Project Highlights
Project Details
Project Highlights
新加坡
  • This project is the first large-scale underground substation project in Southeast Asia.

  • As a developed country, Singapore has particularly stringent requirements for product quality, technology, and services. The successful commissioning of this project not only demonstrates the recognition and leading position of our cable accessory technology in the international market but also reflects the consistent high praise from customers for our service quality.
Project Details
This development plan relocates the substation facilities underground, freeing up three hectares of prime land, equivalent to four football fields. The Labrador Underground Substation aligns with Singapore’s urban renewal strategy and the United Nations Sustainable Development Goals, ensuring reliable and sustainable modern energy for all and promoting sustainable infrastructure. After operation, the substation could met the power demand of nearby towns such as Alexandra, Clementi, Keppel, Pasir Panjang, and Science Park. CYG’s involvement in this project underscores the recognition of our cable accessory technology in the international market, with our service quality also receiving unanimous praise from the client.